Estlink 2 repair work starts in May, scheduled back on line in July

Share

Repair work to the undersea Estlink 2 electricity connection between Estonia and Finland will start next month.According to current estimates, the cable will be back in use and supplying the market from July 15, grid operator Elering said.

The 650-megawatt Estlink 2 was shut down after damage caused by the trailing anchor from oil tanker the Eagle S.on Christmas Day last year.

From February until now, preparations were made to repair the damaged section, which was lifted from the seabed and cut out.